Drainage Rehabilitation and Improvements | ![]() |
||||||||
Original Budget: $ 3,500,000 Revised Budget: $5,900,380 |
|||||||||
PHOTOS |
|||||||||
Project Scope: 1) South Palm Ditch Outfall at Hwy 17 2) Kings Way Outfall Upgrade 3) Coast Guard Drainage Ditch 4) Oak Grove Island Causeway Pipe Rehab 5) Belle Point 6) East Beach 7) Fairway Oaks 8) Barnes Plantation Pumps 9) Buck Swamp Bridge 10) Ocean Blvd 11) Ocean Blvd, Beachview Dr, Breckenridge Subdiv, Harry Driggers, Calebs Crossing & 4th Street Drainage Improvements 12) Glynco Pkwy Bridge 13) Buck Swamp, Ocean, Glynco Drainage Improvements |
|||||||||
|
|||||||||
Project Status: 1) In Progress 2) In Progress 3) In Progress 4) In Progress 5) Complete 6) Complete 7) Complete 8) Complete 9) Complete 10) Complete 11) Complete 12) Complete 13) Complete |
|||||||||
|