Exit #29 Treatment Facility

Exit #29 Treatment Facility
Your dollars at work

Original Budget: $ 8,000,000
Revised Budget: $6,663,582

PHOTOS



Project Scope:
Upgrade the wastewater treatment facility from 0.3 MGD (million gallons per day) to 1.5 MGD. The design also included the capability for an additional 0.5 MGD for reuse water as well as ultimate upgrade to 4.0 MGD.

Project Status:
Completed November 2010




Contact Information
Department: Engineering
Phone: 912 554-7490
Email: [email protected]





Photos