Exit #29 Treatment Facility |

|
Original Budget: $ 8,000,000
Revised Budget: $6,663,582 |
|
PHOTOS
|
Project Scope:
Upgrade the wastewater treatment facility from 0.3 MGD (million gallons per day) to 1.5 MGD. The design also included the capability for an additional 0.5 MGD for reuse water as well as ultimate upgrade to 4.0 MGD. |
|
Project Status:
Completed November 2010 |
|
|
|
|
Contact Information
Department: Engineering |
|
Phone: 912 554-7490
Email: [email protected] |
|
|
|
|